Tuesday, May 12, 2015

Propeller curves , The safety margins in relation to the propeller

Q:- Propeller curves . Enumerate the safety margins in relation to the propeller ..




1. Sea Margin ( SM) ( approximately 15 % power )
The increase in power to maintain a given ship’s speed achieved in  calm weather (point ‘A’ ) and under average service condition (point ‘D’), is defined as the ‘sea margin’. This margin can vary depending on owner’s and charterer’s expectations, routes, season and schedules of the ship. The location of the reference point ‘A’ and the magnitude of the sea margin are determined between the shipbuilder and the owner.
With the help of effective antifouling paints, dry-docking intervals have been prolonged up to 4 or 5 years. Therefore, it is still realistic to provide an average sea margin of about 15 % of the sea trial power.
2. Light running margin (LR)
It is the compensation for loss in RPM between dry docks for constant power operation .
The sea trial performance (curve ‘a’) in figure should allow for a 4 to 7 % light running of the propeller when compared to the nominal propeller characteristic (the example in figure shows a light running margin of 5 %). This margin provides a sufficient torque reserve whenever full power must be attained under unfavourable conditions.
The recommended light running margin originates from past experience.  It varies with specific ship designs, speeds, dry docking intervals, and trade routes. Therefore the ‘light running margin’ required will be 5 to 6 %. This is the sum of the following factors:
a) 1.5–2 % influence of wind and weather with an adverse effect on the intake water flow of the propeller.
b) 1.5–2% increase of ship’s resistance and mean effective wake brought about by:
• Rippling of hull (frame to frame).
• Fouling of local, damaged areas, i.e. boot top and bottom of the hull.
• Formation of roughness under paint.
• Influence on wake formation due to small changes in trim and immersion of bulbous bow, particularly in the ballast condition.
c) 1% frictional losses due to increase of propeller blade roughness
d) 1% deterioration in engine efficiency such as:
• Fouling of scavenge air coolers.
• Fouling of turbochargers.
• Condition of piston rings.
• Fuel injection system (condition and/or timing).
Increase of back pressure due to fouling of the exhaust gas boiler, etc.

3. Engine margin (EM) or operational margin (OM)
Contractual speed is 90 % MCR for most engines. This is the margin allows the  vessel  to  increase  speed  above  the  contractual  speed.  Most  owners

specify the contractual ship’s loaded service speed at 85 to 90 % of the contract maximum continuous rating. The remaining 10 to 15 % power can then be utilized to catch up with delays in schedule or for the timing of dry docking intervals.

4. Shaft Generator Margin (SG) :-
It is given in case a shaft generator is fitted.

Friday, May 8, 2015

Tips to crack MMD written exam..


Tips to crack MMD written exam
  1. Read instruction carefully before start writing. 
  2. Use only one color pen, preferably black or blue, during your exam.
  3. Please don’t use other color pen not even for   headings or underlining. 
  4. Question no. must be written in left hand side margin.
  5.  Don't write it in the  centre of the page or elsewhere.
  6. Do Not leave any blank page Leaving that page blank may leave you disqualified from exam. 
  7. Answer of next question must start from new  page.
  8. Number of pages filled is not of much importance if you know the correct answer of the question.
  9. Be precise and to the point. 
  10. 2- 3 pages for one answer are sufficient.
  11. Sketches leave good impression. It can be drawn free hand,but should be  neat and clear.
  12. Be careful, there should not be failing mistakes in your   sketch.
  13. You must write relevant Regulations Annexes etc. In your answer and underline it. Any specific dates also should be mentioned. All these things give good impression to examiner.
  14. Do not attempt survey related questions. i.e. Boiler survey, Load line   survey etc. Because these answers require specific attention on some important  issues and areas, which you can miss out and this may turn out to be failing mistake.
  15. Questions which require mention of specific Regulations, Annexes, dates   etc. must be written carefully because if you mention correctly, you can   score high, but missing it out can drag your marks down.
  16. First question is always compulsory. Start your answers from question no. 1 only. As attempting it in the last gives an impression that you don't know the subject well.
  17. Please don't make any identification marks on your answer sheet.Also don't write your rotation no. anywhere except the place provided for the same.


Compulsory questions ,mostly minimum 2 questions from this comes in every paper.

compulsory 
 
 
1.   with specific reference to any make, sketch and describe the cylinder lubrication system used in new generation marine diesel engines. how will you effect the optimum cylinder oil feed with varying sulphur content of fuel oil. 
 
 
2.   the protection of the marine environment is of utmost importance today. discuss. (a) how would you as a c/e of a tanker ensure protection of the environment by compliance" with the various regulation of marpol 73/78 annex, 1 for prevention and control of pollution at sea? (b) state the recent requirements of imo for compliance under annex vi of marpol 73/78. 
 
3.   with reference to maritime labour convention (mlc) 2006. briefly discuss the following i) minimum requirements for seafarers working on a ship, ii) conditions of employment. iii) accornodation and recreational facilities, iv) health protection, welfare and social security protection. 
 
4.   what are the major amendments to solas which have entered into force in 2014. briefly discuss any five of them.
 
 
5.   with reference to the underwater surface of a ship's hull: (1) describe a hull plate roughness analyzer system; (ii) state the significance of the roughness profile and compare the typical roughness values for a new ship and a ship eight years old. (b) with reference to the application of self polishing paint in dry dock: (i) describe the plate preparation necessary; (ii) state the defects that may occur in the paint coating if it is not correctly applied. 
 
6.   with respect to annex v of marpol significance of dish water, grey water recycling and reuse. other similar discharges as excluded from the purview of operational wastes and waste minimization (3. with respect to annex v of marpol explain the significance of the following. a) dish water, grey-water recycling & re-use. b) 'other similar discharges' as excluded from the purview of operational wastes; c) garbage maintenance plan and garbage record book: and d) port reception facilities. )
 
7.    define the meaning of the term "conditions of assignment" as applied to ships for load line survey. (b) state how conditions of assignment contribute towards water tight integrity of ships (c) give reasons why conditions of assignment need periodic inspection, giving specific instances where they can be found to be less than fully effective .
 
8.   what are the ongoing developments at the imo with respect to the technical and operational measures to be invoked on board ships for combating green house gas emissions from ships?
 
 
9.   with regards to ordering and receiving fuel bunker on board answer the following a) the importance of correct bunker specification including the relevant iso standard b) how will you ensure that a representative sample is drawn during bunkering? c) how will you ensure that in case of bunker disputes especially with regards to quality the sample from the vessel will be acceptable for verification? 
 
10.   a ship which was bunkering at a foreign port has met with an accident and a substantial amount of oil spillage in water has resulted. draw an emergency preparedness plan for the incident and how best it could be encountered under the provision. describe its salient advantages.(sopep) .
 
11.   Explain in detail the significance of propeller curves to a chief engineer. enumerate the safety margins in relation to the propeller .
 
12.   In an unfortunate incident of main engine crank case explosion on your vessel,the main engine was badly damaged and two engine room personnel suffered serious injuries. explain how you will present the vessel for subsequent inspections by p&i and h&m insurance companies with special emphasis on the records and documents required in each case to ensure that only genuine claims are honored. 
 
 
13.   With respect to eedi explain in detail the following. required eedi ,attained eedi .
 
14.   The ism code stipulates that safety management objectives of the company, should inter alia assess all identified risk to its ships personal and the environment and establish appropriate safe guards, how will you as the chief engineer assist the company in fulfilling this objective? 
 
15.   A junior engineer has joined ship. Enumerate in detail the issue you would mentor him or her with respect to the following: up keep of his personal safety, up keep of the safety of his colleagues on board, technical job, responsibility he need to learn at the earliest, what attention he needs to pay towards energy conservation and his entitlement with regard to human right in a foreign port. 
 
16.   your vessel where you are posted as a chief engineer is about to enter dry dock. State the co- ordination and information exchange necessary with the master of the vessel for successful entry. also list the necessary preparation you would make along with earmarking division of duties to the engineers of the vessels. enlist the inspection and co-ordinations you will make with dry dock authorities for successful coming out of the dry dock.  
 
17.   What are the significant solas amendments coming into force in 2013? with reference to solas 2010 amendment, discuss "international goal based ship construction standards? 
 
18.   you are the chief engineer of a vessel that has suffered a minor fire in the engine room that burned off the wiring to essential pumps. temporary repairs were made to get the vessel underway. write a letter to the company head office describing the incident as to how the fire took place and what corrective and preventive steps have you taken. what arrangements do you suggest to affect a permanent repair at the next port of call? 
 
19.   Vent pipes have a special role to play with respect to safety of ships please explain in detail the following where these are fitted any special fitment requirement as per statutes. 
 
20.   Your vessel has been awarded 3 major non conformities during sms audit. Frame a report in the format of an email addressing the engineer superintendent with suggested step to be taken for early sailing of the vessel.
 
21.   In relation to sea worthiness of a ship discuss the responsibility and authority of the following stake holder: maritime administration, recognized organization, shipowner,  insurance company. 
 
22.   What do you understand by unseaworthy vessel within the meaning of the msa 1958 as amended? what according to you is the difference between unseaworthy and   unsafe ship ?what are the obligation of the owner to crew with respect seaworthiness. 
 
23.   How will you prepare your ship for a renewal survey of iappc international air pollution prevention certificate! explain with specific emphasis on the records and documents to be maintained.enumerate general requirements for shipboard incinerators, as mentioned in annex vi of marpol 73/78.
 
24.   The ism code stipulates that the safety management objectives of the company should inter alia assess all identified risks to its ships,  personnel and establish appropriate safeguards. how will you as a chief engineer assist the company in the fulfilling this objective?

    Thursday, April 30, 2015

    To order and receive fuel bunker on board ENSURING CORRECT QUANTITY

    With regards to ordering and receiving fuel bunker on board, How will you ensure that in case of bunker disputes, especially with regards to quantity .


     ENSURING CORRECT QUANTITY:-



      After bunkering Bunker quantity disputes can arise due to 
    1. Measured volume of barge is different from BDN
    2. Measured volume for barge is different from ship’s figure
    3. Weight of bunkers delivery note calculated with incorrect density 
    4. High water content
    5. Cappuccino bunker (air foam in bunkers) 
    Normally up to 1% discrepancy in quantity is tolerated and if exceeds ‘letter of protest’ must be written by master ad an independent surveyor to be called for investigation .
    In case of any dispute regarding quantity of bunker received, the chief engineer of vessel should raise a note of protest which shall be signed by both parties. 
    Letter of protest (claim limit- qty :- 15days / quality :- 30days)

    • Addressed to
    • Made from
    • Date ,time & port
    • Details of dispute
    • Copy to charter
    • Copy to company
    • Copy to supplier flag state
    • Letter of protest by supplier


    An independent surveyor may then be called to investigate the findings. This should be  entered in log book or an oil record book.




       
    However, the following minimum steps are recommended :

    1. Immediately notify the parties concerned and appoint an independent surveyor if not already done so and do not disconnect hoses.
    2. Re-do the entire gauging, check and re-check both pre and post bunkering calculations making sure the list/trim corrections have been correctly applied.
    3. Verify correct temperatures and densities have been used.
    4. Issue letter of protest for each incident and have it acknowledged by the barge (note the barge Master will probably refuse to acknowledge such letters).
    5. Write up a detailed statement of facts leading to the short delivery.
    6. Preserve any evidence e.g. if you suspect froth on the surface of the fuel / too many bubbles on the sounding tape then taking photographs would be prudent.
    7.   A success of a claim will largely depend on the nature and the quality of evidence gathered at the time the supply is made.If there is detailed contemporaneous written evidence, the ship operator will be in a much stronger position in case of subsequent litigations.
    8. Further, it may be necessary for full disclosure of the supplier's stock movement reports to ensure that the original supplied quantity tallied with the quantity at the time of opening gauge.
    9. Another tactic we have seen is "pilot onboard" – this may seem like a stalemate and to the supplier's advantage (delaying the vessel's departure it never a good thing) but with careful handling of the situation the agent should be advised beforehand to postpone the pilot boarding thus giving the vessel sufficient time to resolve / deal with the dispute.
    10. The barge outturn figure (delivered fuel quantity) will be recorded on the BDN for  invoice purposes. In case of a short fuel delivery a note of protest must be issued and the same reflected in the Oil Record Book (ORB) and do not sign the BDN as presented but sign only for the soundings and ship's volume.

    Wednesday, April 29, 2015

    Harmonized system of survey and certification ,hssc survey

    Q:-Explain Harmonization of Statutory Certificates under the   SOLAS 74/88 Convention.
    If a period of a statutory Certificate has just expired and a port is having inadequate survey facility, state the actions you will take, as per the provision stated in the Protocol of 1998 relating to the International Convention for the Safety of Life at Sea, 1974.


    ANSWER :-

    A harmonized system of survey and certification covering international shipping regulations adopted by the International Maritime Organization enters into force on 3 February 2000, in order to alleviate the problems caused by survey dates and intervals between surveys which do not coincide, covering international shipping regulations including the codes and conventions of these following institutions:

    1. International Convention for the Safety of Life at Sea (SOLAS), 1974
    2. The International Convention on Load Lines (LL), 1966
    3. The International Convention for the Prevention of Pollution from Ships, 1973, as modified by the Protocol of 1978 relating thereto -MARPOL 73/78
    4. The International Code for the Construction and Equipment of Ships Carrying Dangerous Chemicals in Bulk (IBC Code)
    5. Code for the Construction and Equipment of Ships Carrying Dangerous Chemicals in Bulk (BCH Code)
    6. Code for the Construction and Equipment of Ships Carrying Liquefied Gases in Bulk (IGC Code).

    Purpose
         Surveys, made in accordance with the harmonised survey system for ships, to harmonize intervals between surveys of all legitimate certificates issued to all marine vessels. 
           The harmonized system is presumed to facilitate all the troubles of periods between  surveys so that any ship would not have to worry about going into the process of a survey schedule required by one convention right after having gone through the same thing concerned in connection with another instrument.


    Harmonized system adopted in 1988:-this is just for refrence
        The international requirements introducing the harmonized system of survey and certification for the SOLAS and Load Lines Conventions were adopted by IMO at an International Conference on the Harmonized System of Survey and Certification held in 1988 - which itself had its origins in the 1978 Conference on Tanker Safety and Pollution Prevention which recognized the difficulties caused by the survey and certification requirements of SOLAS, the Load Lines Convention and MARPOL 73/78. The 1978 Conference called upon IMO to develop a harmonized system which would enable the surveys to be carried out at the same time.
          The 1988 HSSC Conference adopted Protocols to the SOLAS and Load Lines Conventions to introduce the harmonized system. 
          The conditions for entry into force of the 1988 SOLAS and Load Lines Protocols were met on 2 February 1999, when Bahamas deposited instruments of accession to both instruments with IMO. Malta also recently acceded to the 1988 Protocols. The 1988 Load Lines Protocol has 36 States Parties with 58.58 percent of world merchant shipping tonnage. The 1988 SOLAS Protocol has 36 States Parties with 58.10 percent of world merchant shipping tonnage.
        In terms of MARPOL 73/78, the Convention allowed for amendments to the certification and survey requirements to be accepted by a procedure known as "tacit acceptance", meaning amendments enter into force on a specified date unless sufficient objections are received. 
        As a result, MARPOL 73/78 was amended on 16 March 1990 to introduce the harmonized system of survey and certification, with the proviso that the amendments enter into force at the same time as the  entry into force date of the 1988 SOLAS Protocol and the 1988 Load Lines Protocol.

    List of certificates required on board ship relating to harmonized system of survey and certification (some depend on type of ship)
    1. Passenger Ship Safety Certificate, including Record of Equipment
    2. Cargo Ship Safety Construction Certificate
    3. Cargo Ship Safety Equipment Certificate, including Record of Equipment
    4. Cargo Ship Safety Radio Certificate, including Record of Equipment
    5. Cargo Ship Safety Certificate, including Record of Equipment
    6. International Load Lines Certificate(ILLC)
    7. International Load Lines Exemption Certificate
    8.  International Oil Pollution Prevention Certificate
    9.  International Pollution Prevention Certificate for the Carriage of Noxious Liquid  Substances in Bulk.
    10.  International Certificate of Fitness for the Carriage of Dangerous Chemicals in Bulk
    11.   International Certificate of Fitness for the Carriage of Liquefied Gases in Bulk
    12.   Certificate of Fitness for the Carriage of Dangerous Chemicals in Bulk

    The harmonized system

    In practice, many Administrations and classification societies already operate a form of harmonized survey and certification. Moreover, a resolution adopted by the IMO Assembly in 1991, and amended in 1993 (Resolution A.718(17), as modified by resolution A.745(18)), allowed for Governments which had ratified the 1988 SOLAS and Load Lines Protocols to implement the harmonized system ahead of the entry into force date of the protocols.

    The harmonized system provides for:
    • A one-year standard interval between surveys, based on initial, annual, intermediate, periodical and renewal surveys as appropriate;
    •  A scheme for providing the necessary flexibility for the execution of each survey with the provision that the renewal survey may be completed within three months before the expiry date of the existing certificate with no loss of its period of validity;
    • A maximum period of validity of five years of all certificates for cargo ships;
    • A maximum period of validity of 12 months of the Passenger Ship Safety  Certificate;
    • A system for the extension of certificates limited to three months to enable a ship to complete its voyage (or one month for ships engaged on short voyages);
    •  When an extension has been granted, the period of validity of the new certificate is to start from the expiry date of the existing certificate before its extension.

          The main changes to the SOLAS and Load Lines Conventions are that annual inspections have been made mandatory for cargo ships and unscheduled inspections have been discontinued. Other changes refer to survey intervals and requirements.
           No more unscheduled inspections for harmonised system of classification for ships, while  annual surveys have been made mandatory
           At least two inspections are required to be executed of the ship’s bottom in a five year          period; maximum interval between the inspections has also been set at not more than thirty six months.

            A substantive harmonised system for merchant marine which credits a combined cargo ship safety certificate to replace existing safety equipment, safety construction and safety  radio certificates